Not on the Commissioners Court agenda yet
The court said it will notify the public when it is. Sign up and we’ll tell you the date.
-
Expected Dec. 2026
State audit expected to end — and the permit freeze with it
Gov. Abbott’s freeze on state data-center permits lasts only until ERCOT’s audit ends. After that, permits could flow again. That’s why local action matters now.
-
Sept. 21, 2026
Governor orders TCEQ to halt data-center permits
The order covers off-grid power plants like the one proposed here, and runs until ERCOT’s audit is done.
-
Sept. 15, 2026
Pacifico presents to the Commissioners Court
At a special workshop, Pacifico Energy described an off-grid gas power plant and AI data center on the Ahern Ranch, modeled on its Pecos County project. It named no water source, no plant size and no final site. Judge Henington said no agreements have been signed. Residents from Terlingua to Marathon spoke, and none spoke in favor.
-
Aug. 3, 2026
Governor pauses data-center grid hookups
Gov. Abbott ordered a pause on connecting new data centers to the state grid. Off-grid plants like Pacifico’s don’t need a grid hookup to run.
-
Feb. 2, 2026
The Pecos County model’s permit numbers come out
Pacifico’s GW Ranch in Pecos County, now owned by Amazon, is permitted for 7.65 GW and up to 33 million tons of greenhouse gases a year (The Texas Tribune).